No. 80/2017  |  19-06-2017

Realisation of the Power plant in Wloclawek investment completed

PKN ORLEN S.A. hereby informs that on 19 June 2017 it signed with the consortium of companies (General Electric International Inc. acting via General Electric International S.A., office in Poland and SNC-LAVALIN POLSKA sp. z o.o.) (“Contractor”) a certificate on the base of which the realisation of investment of the Power plant in Wloclawek (“Power plant”) building has been completed.

The total CAPEX spent by PKN ORLEN S.A. for the project of the Power plant building amounted to ca. PLN 1,4 bn.

See also: regulatory announcement no 241/2012 dated 30 November 2012, regulatory announcement no 249/2012 dated 4 December 2012, regulatory announcement no 129/2015 dated 16 September 2015, regulatory announcement no 181/2016 dated 30 June 2016, regulatory announcement no 197/2016 dated 19 July 2016, regulatory announcement no 17/2017 dated 25 January 2017.