No. 165/2017  |  21-12-2017

Information regarding CCGT that is being built in Płock

PKN ORLEN S.A. informs that the usage permit for CCGT cogen-plant (“Power plant”) ,located within Production plant in Płock (“Production plant”) is planned to be obtained in the first quarter of 2018.

After successful synchronization of the Power plant with the Polish Power System in September 2017 and reaching the maximum power output of ca. 600 MWe in November 2017, the Power plant delivered steam to the Production plant for the first time in December 2017. Currently a number of activities are conducted in order to obtain the usage permit for the Power plant.
 
See also: regulatory announcement no 287/2014 dated 2 December 2014, regulatory announcement no 281/2014 dated 26 November 2014.